Latest Issue
 
Windtech International November December 2024 issue

 

FOLLOW US AT

follow

 

follow


RWE has started constructing the Mondonuovo wind farm in the Apulia region of south-east Italy. In the first construction phase, access roads to the site are adjusted and crane erection areas are built.
 
The team then pours the 20-metre-high foundations and erects the towers. RWE uses special blade lifter technology to transport the rotor blades, allowing them to navigate tight bends and alleyways. Nine turbines will be installed, each with a capacity of 5.9MW. The 53MW Mondonuovo wind farm is scheduled to be commissioned in 2025.
 
Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.